Green Valley (Khilkhet) Housing Project-1

Green Valley (Khilkhet) Housing Project-1 is the society's largest active housing project. The project is planned over approximately 314.47856 bighas of land. The society has purchased or exchanged 249.9946 bighas in the project name, of which 235.1542 bighas fall inside the approved layout and have been mutated in the society's name. Development work is progressing across land regularization, internal roads and drains, electricity, water supply, mosque construction, school facilities, lake planning, and boundary/security infrastructure.

Green Valley (Khilkhet) Housing Project-1
housing
Running
Active development and land regularization underway
Location
Under Khilkhet Police Station, adjacent to the 300 Feet Road, Dhaka
Category
housing
Current Status
Active development and land regularization underway
Completion
--

At a Glance

Project NameGreen Valley (Khilkhet) Housing Project
Number of Project Members2,278 members
Mouzas Included in the ProjectTalna, Mastul, Dumni, Dhelna, Baothar, Barua
Land Included in the Layout103.77792 acres or 314.47856 bighas
Unexchanged Land Included in the Layout22.206855 acres or 67.2935 bighas
Land Purchased/Exchanged in the Society’s Name Within the Layout77.600886 acres or 235.1542 bighas
Layout Plan Summary
DescriptionNumberAllocated Land Area
Total Residential Plots (10 Kathas)285142.51 bighas (47.11 acres)
Educational Institutions211.22 bighas (3.71 acres)
Medical College and Hospital13.81 bighas (1.26 acres)
Mosque11.54 bighas (0.51 acres)
Community Center11.66 bighas (0.55 acres)

Overview

The total land area of the Khilkhet Housing Project is approximately 314.47856 bighas. The society has purchased and mutated 235.1542 bighas in its own name.

The layout includes 9.05469 bighas of khas land, 7.01636 bighas of Union Parishad and Court of Wards land, and 67.2935 bighas that still need exchange or purchase. Early action is needed to exchange and register the remaining land in the society's name.

The project is progressing across several areas, including plot registration, model mosque construction, internal roads and drainage, DESCO electricity infrastructure, water supply planning with Dhaka WASA, school establishment, lake excavation, and a proposed security wall with a July Memorial plaque.

Key Facts

Total land area
Approximately 314.47856 bighas
Land mutated in the society's name
235.1542 bighas
Union Parishad and Court of Wards land
7.01636 bighas
Recently active exchange with Bashundhara Group
0.5892 bighas
Registration phase dates
16.07.2025, 20.07.2025, and 10.08.2025
Installed DESCO poles
154 poles installed so far
Land purchased by the society
235.1542 bighas
Khas land inside the layout
9.05469 bighas
Land still needing exchange or purchase
67.2935 bighas
Registered unencumbered plots
163 of 285 plots in two phases
Internal road DPP approval
BDT 49.7540 crore approved by ECNEC on 09 November 2023
Total land purchased/exchanged in the project name
249.9946 bighas
Land outside the project area
14.8404 bighas
Land inside approved layout and mutated in society name
235.1542 bighas
Total non-purchased land inside approved layout
79.32436 bighas
Remaining exchange/purchase land after school adjustment
67.2935 bighas
Government primary school land
35 decimals
Model mosque land
51.33 decimals
Total plots / registered so far
285 / 163
More plots are cleared for registration after owners submit documents/pay orders
22
Shares allotted to 11 deprived members, under decisions dated 11.10.2025 and 03.04.2026
11

Project Gallery

Milestones

  • •Land registration completed for 67 unencumbered plots in two phases during July and August 2025.
  • •Base type-1 work on the connecting road from the 300 Feet Road has been completed; carpeting remains pending.
  • •The project has been included in the proposed Expanded Dhaka City Water Supply Resilient Project of Dhaka WASA.
  • •Model Mosque construction by the Islamic Foundation is in progress on 51.33 decimals, roof casting/slab completion.
  • •The Ministry of Primary and Mass Education sent a follow-up letter on 05.02.2025 regarding an aesthetically designed primary school in the project area.
  • •Soil tests for the internal lake have been completed after site visits by Water Development Board engineers.
  • •In 2025, current committee acquired/exchanged 0.78936 acres / 2.392 bighas
  • •In first half of 2026, current committee acquired/exchanged 0.394 acres / 1.1969 bighas
  • •Government primary school administrative approval received
  • •RFP for 8 prototype residential building designs published on 31.03.2026 RFP pre-bid meeting held on 20.04.2026 RFP submission deadline extended to 21.05.2026
  • •11 shares allotted to deprived members under official decisions

Open Items

  • •Exchange and register the remaining 67.2935 bighas included in the project layout.
  • •Complete carpeting of the connecting road from the 300 Feet Road.
  • •Prepare and submit the relevant DPPs for lake, riverbank, canal, and protection works through the proper ministries.
  • •Construct the proposed eastern security wall with a July Memorial plaque after estimate finalization.
  • •Remaining exchange/purchase land after school adjustment: 67.2935 bighas still needs settlement
  • •Total non-purchased land inside approved layout: 79.32436 bighas; requires further purchase/exchange/legal settlement
  • •DESCO future work: 306 more electric poles expected
  • •RFP for 8 prototype residential building designs for 10, 20, and 40 katha plots needs final selection and implementation
  • •Plot registration pending: 122 plots still unregistered out of 285
  • •22 cleared plots need owner document submission and pay order completion
  • •Government secondary school land adjustment for 1.5462 acres / 4.6855 bighas needs final legal/financial settlement if not completed
  • •Government primary school has administrative approval, but construction/implementation may still need follow-up

Status Note

Land purchase, exchange and legal settlement, plot registration, and road, electricity, water, mosque, school and other infrastructure work are continuing.